January 2012 : https://www.pdfquestion.in/uploads/nielit.in/7084-jan12A102-R4.pdf
JULY 2012 : https://www.pdfquestion.in/uploads/nielit.in/7084-jul12A102-R4.pdf
January 2013 : https://www.pdfquestion.in/uploads/nielit.in/7084-jan13A102-R4.pdf
JULY 2013 : https://www.pdfquestion.in/uploads/nielit.in/7084-jul13A102-R4.pdf
January 2014 : https://www.pdfquestion.in/uploads/nielit.in/7084-jan14A102-R4.pdf
July 2014 : https://www.pdfquestion.in/uploads/nielit.in/7084-jul14A102-R4.pdf

NIELIT Software Testing Sample Paper

A10.2-R4:

PART ONE

(Answer all the questions)
1. Each question below gives a multiple choice of answers. Choose the most appropriate one and enter in the “tear-off” answer sheet attached to the question paper, following instructions therein. (1×10)

Related : NIELIT Question Paper A Level Course Introduction to Object Oriented Programming Through Java : www.pdfquestion.in/7083.html

1.1 Which of the following statistical tools can be used to represent a large amount of data in simple chart form?
A) Cause and effect diagram
B) Histogram
C) Pareto chart
D) Control chart
1.2 Test are prioritized so that
A) You shorten the time required for testing
B) You do the best testing in the time available
C) You do more effective testing
D) You find more faults
1.3 The inputs for developing a test plan are taken from
A) Project plan
B) Business plan
C) Support plan
D) None of the above


1.4 Which of the following is not a part of the Test Implementation and Execution Phase?
A) Creating test suites from the test cases
B) Executing test cases either manually or by using test execution tools
C) Comparing actual results
D) Designing the Tests
1.5 A Peson who documents all the issues, problems and open points that were identified during a formal review is known as
A) Moderator
B) Scribe
C) Author
D) Manager
1.6 A Verification is
A) Checking that we are building the right system
B) Checking that we are building the system right
C) Performed by an independent test team
D) Making sure that it is what the user really wants
1.7 Static analysis is best described as
A) The analysis of batch programs.
B) The reviewing of test plans.
C) The analysis of program code.
D) The use of black box testing.
1.8 With the acquisition of a testing tool, the test engineer’s first priority is to
A) Decide how much to pay
B) Check with end-user first
C) Identify the goal for the tool usage
D) Make sure that the management agrees to the use of the tool
1.9 What can you use to select an object as a verification point?
A) the object finder, the object picker, or the object browser
B) the main object browser, the test object browser, or the extra object browser
C) the object finder, the test object browser, or the delay method
D) the delay method, the scripting method, or the pointer method
1.10 Data collected during testing should include
A) Test Factors
B) Functions/subroutines
C) Platforms
D) All of the above
2. Each statement below is either TRUE or FALSE. Choose the most appropriate one and ENTER in the “tear-off” sheet attached to the question paper, following instructions therein. (1×10)
2.1 One of the features of Object Oriented programming is: Emphasis on procedure rather than data.
2.2 Function/Test matrix is a type of Project status report.
2.3 Faults in requirements are the most expensive to fix.
2.4 Functional testing technique helps to ensure that the requirement/specifications are properly satisfied by the software system.
2.5 When DLL files are unregistered or removed, due to uninstalling or installing, is called DLL Hell.
2.6 Water fall model is the one of the model of software testing.
2.7 Static linking and window file protection is a solution for the conflicting DLL Problems.
2.8 The purpose of boundary value analysis is to concentrate the testing effort on error prone areas by accurately pinpointing the boundaries of conditions.
2.9 Performance testing can be done during unit testing as well as during the testing of whole system.
2.10 Alpha testing is post-release testing by end user representatives at the developer’s site.

PART TWO

Answer any FOUR questions :
5. a) It is observed that the testers in your organization are performing tests on the deliverable even after significant defects have been found. This has resulted in unnecessary testing of little value because re-testing needs to be done after defects have been rectified. You are the test manager and going to update the test plan with recommendations on when to stop testing. List the recommendations you are going to make.
b) What is the role of QAG (Quality Assurance Group) in project development?
c) What are the key challenges of software testing? (6+5+4)

1 Comment
Add a Comment
  1. I need the solution for Software testing.

Leave a Reply

How to add comment : 1) Type your comment below. 2) Type your name. 3) Post comment.

www.pdfquestion.in © 2021

Contact Us   Privacy Policy   SiteMap