GTU Hydrology & Water Resources Engineering Question Paper
Download Question Paper of Hydrology & Water Resources Engineering 2019 Sample Question is now available in the official website of Gujarat Technological University.
Related : GTU Gujarat Technological University Current Semester B.Pharm Exam Paper 2018 : www.pdfquestion.in/29945.html
Subject Code: 2150602
Date: 20/06/2019
Time: 02:30 PM TO 05:00 PM
Total Marks: 70
Download Question Paper :
https://www.pdfquestion.in/uploads/pdf2019/34356-HWRE.pdf
Instructions
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
Sample Questions
Q.1 (a) Calculate the average annual rainfall using Theissen polygon method for the following data:
Rain gauge station
(b) Give the name of automatic rain gauges and explain any one in detail with figure. 04
(c) Explain in detail with neat sketch the double mass curve technique to check the consistency of rainfall data. 07
Q.2 (a) Explain the Rational Method for estimation of peak flood discharge. 03
(b) Explain Darcy’s law with figure. 04
(c) In a certain river basin, there are four rain gauge stations, with their normal annual precipitation amounting to 800, 520, 450 and 390 mm, respectively. Determine the optimum number of rain gauges in the catchment, if it is desired to limit the error in the mean value of rainfall in the catchment to 10 %. 07
OR
(c) A thunder storm of 6hour duration produces the following flood hydrograph. Derive the ordinates of unit hydrograph for a catchment area of 2845 km2. Also sketch the resulting unit hydrograph. Date
Q.3 (a) Describe in brief Reservoir sedimentation 03
(b) Describe the situations under which the following dams are constructed
(1) Gravity dam (2) earthen dam 04
(c) Discuss occurrence of groundwater with a neat sketch and define various water bearing formations. 07
OR
Q.3 (a) Write a brief note on flood damage analysis. 03
(b) Define following terms: (i) Firm Power, (ii) Load Factor, (iii) Gross Head, (iv) Operating Head 04
(c) Explain the mass curve method that can be used for determining reservoir capacity. 07
Q.4 (a) Discuss the measures to be adopted for water conservation in water scarce regions.03
(b) Distinguish between (1) Hydraulic and hydrologic method of flood routing (2) Hydrologic storage routing and hydrologic channel routing
(c) Define the following with figure (1) Earthen dam (2) Gravity dam (3) Arch dam (4) Buttress dam (5) Spillway 07
OR
Q.4 (a) What is the need for planning of water resources projects? 03
(b) Define ‘Drought’. Distinguish between hydrological drought and meteorological drought. 04
(c) Explain with a neat sketch the components of a hydroelectric power plant. 07
Q.5 (a) Discuss the factors affecting infiltration.03
(b) Discuss the Penman-Monteith method for evapotranspiration estimation. 04
(c) Define flood and its causes. Also discuss various measures taken to control the flood. 07
OR
Q.5 (a) Define the following with figure (1) Infiltration index (2) Specific yield 03
(b) Define unit hydrograph and its applications. 04
(c) Enlist various methods of flood estimation. Describe flood frequency analysis. 07